What City Hall said it would do

22 commitments, followed from the vote or statement to the latest public evidence we could identify. An approved budget is not counted as a completed project.

22commitments tracked
1delivered
8partial / on watch
13not publicly verified
Read the status carefully.

“Not publicly verified” does not mean the work was not done. It means the public record reviewed here does not yet prove completion. The City can correct or update any entry with documentation.

Issue
Status
Governance · Administration commitment

Provide council with an accessibility report following the November delegation.

Not publicly verified
On recordNovember 28, 2023
Age at review1022 days
ResponsibleCity Administration
DeadlineNo deadline stated
What the record proves

The written minutes record that staff would provide a report.

What remains

The report and a recorded council response have not been matched in the indexed public record.

November 28 minutes
Public safety · Administration commitment

Return with information on by-laws and mechanisms for prompt removal of abandoned or crashed vehicles.

Not publicly verified
On recordNovember 28, 2023
Age at review1022 days
ResponsibleCity Administration
DeadlineNo deadline stated
What the record proves

Administration agreed to review the available tools and report back.

What remains

The promised report has not been matched in the indexed public record.

November 28 minutes
Public safety · Administration commitment

Present a public-safety plan or program to council.

Partial
On recordNovember 28, 2023
Age at review1022 days
ResponsibleCity Administration
DeadlineLater meeting; no date stated
What the record proves

Council later debated the Public Safety Committee and an internal interagency working group, but that does not by itself establish delivery of the promised plan.

What remains

A clearly identified plan or program matching the commitment remains to be located.

November 28 minutes
Water · Administration commitment

Provide detailed monthly long-term-water reporting and a concise executive summary to council.

Not publicly verified
On recordDecember 12, 2023
Age at review1008 days
ResponsibleLong-term water project team
DeadlineMonthly
What the record proves

The project team said dashboard material was available and accepted monthly reporting in principle.

What remains

A complete public series of monthly executive summaries has not been located in the indexed record.

December 12 minutes
Governance · Administration commitment

Review the scrap-metal contract and determine whether the City receives proceeds from metal sales.

Not publicly verified
On recordFebruary 6, 2024
Age at review953 days
ResponsibleCity Administration
DeadlineNo deadline stated
What the record proves

The CAO said he would review the contract terms after Mayor Awa asked whether the City received money from scrap-metal removal.

What remains

A public answer identifying any sale proceeds has not been matched in the indexed record.

February 6 Finance minutes
Governance · Adopted motion

Examine creation of an Outdoor Sports Park Reserve Fund during the budget-amendment process.

Not publicly verified
On recordApril 9, 2024
Age at review890 days
ResponsibleCity Administration
Deadline2024 budget-amendment process
What the record proves

Council adopted Motion 24-91 after removing a proposed $500,000 amount from the direction.

What remains

The final reserve amount and implementation result have not been matched in the indexed record.

April 9 minutes
Governance · Adopted motion

Develop a new recreation-program registration system.

Not publicly verified
On recordSeptember 24, 2024
Age at review722 days
ResponsibleCity Administration
DeadlineNo deadline stated
What the record proves

Council adopted Motion 24-296 by a recorded 5–1 vote.

What remains

The launch date, procurement route and final system have not been matched in the indexed public record.

September 24 minutes
Governance · Administration commitment

Present terms of reference for the new Governance and Priorities Committee at the next council meeting.

Delivered
On recordFebruary 11, 2025
Age at review581 days
ResponsibleCity Administration
DeadlineNext council meeting
What the record proves

Draft terms were presented February 25 and committee appointments were completed March 11.

What remains

No missing delivery is identified for this commitment.

February 11 minutes
Public safety · Administration commitment

Provide council with the Fire Department Needs Assessment requested during the eight-storey housing discussion.

Not publicly verified
On recordApril 8, 2025
Age at review525 days
ResponsibleCity Administration
DeadlineNo deadline stated
What the record proves

The written minutes record Flaherty's request for the assessment.

What remains

Delivery of the assessment to council is not confirmed in the indexed public record.

April 8 minutes
Planning · Staff target

Register the quarry survey within the two-to-three-week timeframe stated by Planning.

Not publicly verified
On recordMay 20, 2025
Age at review483 days
ResponsiblePlanning and Development
DeadlineTwo to three weeks
What the record proves

Planning gave the registration estimate while answering Mayor Awa.

What remains

A registration date or registered survey was not matched in the indexed record.

May 20 minutes
Public safety · Administration commitment

Return with a report explaining low Motor Vehicle Act enforcement numbers.

Not publicly verified
On recordJune 10, 2025
Age at review462 days
ResponsibleRCMP / City liaison
DeadlineNext meeting
What the record proves

The RCMP promised a report at the next meeting after Stevenson questioned the numbers.

What remains

The promised follow-up report was not identified in the indexed minutes.

June 10 minutes
Roads · Staff target

Address Plateau traffic-calming measures after the planned 2026 paving work.

On watch
On recordSeptember 25, 2025
Age at review355 days
ResponsibleCity Administration
DeadlineOperating plan for 2027
What the record proves

Administration tied traffic calming to the period after capital-funded paving.

What remains

The 2027 operating decision and specific safety measures remain future records.

September 25 Finance minutes
Governance · Adopted motion

Present regular summary reports from the internal Public Safety Interagency Administrative Working Group to council.

Not publicly verified
On recordJanuary 27, 2026
Age at review231 days
ResponsibleCity Administration
DeadlineNo interval stated
What the record proves

Motion 26-14 makes regular reports part of the approved replacement model.

What remains

No standalone summary under the working group’s name was identified in the public records indexed through August 25.

January 22 minutes
Governance · Administration commitment

Bring a detailed update from each City department to Governance and Priorities every three months.

Partial
On recordMarch 3, 2026
Age at review196 days
ResponsibleCity Administration
DeadlineEvery three months
What the record proves

The May 5 meeting contains a detailed Fire Department update.

What remains

A public schedule showing when every department reported and when each is due back was not identified.

March 3 minutes
Governance · Administration commitment

Create a regular public-engagement route through Governance and Priorities and develop town-hall opportunities.

Partial
On recordMarch 3, 2026
Age at review196 days
ResponsibleCouncil and Administration
DeadlineNo final calendar stated
What the record proves

The May 5 agenda includes a dedicated Public Engagement Items section.

What remains

A complete town-hall calendar and a clear explanation of how residents place items on the agenda remain to be verified.

May 26 package (includes May 5 minutes)
Governance · Implementation obligation

Move the subjects and unfinished work of the former committees into the new Governance and Priorities structure.

Not publicly verified
On recordMarch 24, 2026
Age at review175 days
ResponsibleCouncil and Administration
DeadlineNo deadline stated
What the record proves

Motion 26-51 folds the existing committees into Governance and Priorities Committee of the Whole.

What remains

No public crosswalk listing every former committee, its unfinished files and the new reporting location was identified.

March 24 council record
Water · Adopted motion

Complete the Ulu Lane piped-water system at the same time as the piped sewer work using an $860,000 capital amendment.

Not publicly verified
On recordMarch 24, 2026
Age at review175 days
ResponsibleCity Administration
DeadlineNo completion date stated
What the record proves

Council unanimously approved Motion 26-49.

What remains

A public completion certificate, updated schedule or final cost was not identified in the indexed record.

March 24 council record
Water · Adopted motion

Deliver $3.925 million in Lift Station No. 1 protection and AV205–AV601 sewer upgrades.

Not publicly verified
On recordMarch 24, 2026
Age at review175 days
ResponsibleCity Administration
DeadlineNo completion date stated
What the record proves

Council unanimously approved Motion 26-47.

What remains

Procurement, construction progress and final cost remain to be matched to later public records.

March 24 council record
Planning · Staff target

Present the updated General Plan and Zoning By-law to council.

On watch
On recordMay 26, 2026
Age at review113 days
ResponsiblePlanning and Development
DeadlineFall 2026
What the record proves

Administration told council in both the minutes and full recording that the updated plan and by-law were in their final phases and would return that fall.

What remains

The final drafts, public-review schedule and council disposition remain to be matched to a later public record.

May 26 meeting record and audio
Roads · Adopted motion

Carry out the 2026 Road Improvement Project under the $6.441-million contract awarded to Pilitak Enterprises.

Partial
On recordJune 23, 2026
Age at review84 days
ResponsibleCity Administration and contractor
DeadlineContract schedule not in registry
What the record proves

Motion 26-131 records the contract award.

What remains

The motion registry does not establish percent complete, streets finished, change orders or final cost.

June 23 motion registry
Planning · Administration commitment

Bring council a request for decision and possible policy on delegating compliant annual quarry-permit renewals while preserving council oversight.

On watch
On recordJune 16, 2026
Age at review91 days
ResponsibleCity Administration
DeadlineFall 2026
What the record proves

During the full June 16 recording, the CAO committed to returning in the fall after councillors expressed both support and concern about delegated authority.

What remains

No resulting request for decision or policy was identified in the public records indexed through August 25.

June 16 meeting record and audio
Housing · Staff target

Work toward the 2027 construction season for the Tundra Ridge development, subject to required approvals.

On watch
On recordJuly 28, 2026
Age at review49 days
ResponsibleDeveloper and City Administration
Deadline2027 construction season
What the record proves

Staff told council the selected proposal contained a detailed schedule and identified 2027 as the target season.

What remains

The public should be able to compare permits, lease execution and site work with the target as each milestone occurs.

July 28 council package
01

Classify the words

An adopted motion, an administration commitment and a staff target are not treated as the same thing.

02

Follow the evidence

Later minutes, registries, contracts and reports are matched back to the original commitment.

03

Show what is missing

Authorization is not completion. When the public record stops, the tracker says so plainly.